Construction Update from Pepco Project on Randolph Road and Nebel Street

Construction Update from Pepco Project on Randolph Road and Nebel Street

Week of 11/08/2021

Nebel St.-Package C (CW & Sons)-Continue 4-way excavation around manholes

CSX/Randolph Rd.-Package A/B (SECA)-Pour concrete-Mount seal assembly

Nebel St. & Marinelli -Package-A (CW & Sons Crew #2)-Complete box tunnel-Continue excavation to stubs


Week of 11/15/2021

CSX/Randolph Rd.-Package A (SECA)-Begin first drive


Nebel St. & Marinelli Rd.-Package A (CW & Sons Crew #2)-Install conduits to tie onto stubs-Pour concrete-Backfill/temporary asphalt


Nebel St.-Package C (CW & Sons)-Continue getting trench to grade near sewer line-Begin excavation along substation wall

Amy Ginsburg