Construction Update from Pepco Project on Randolph Road and Nebel Street
Week of 11/08/2021
Nebel St.-Package C (CW & Sons)-Continue 4-way excavation around manholes
CSX/Randolph Rd.-Package A/B (SECA)-Pour concrete-Mount seal assembly
Nebel St. & Marinelli -Package-A (CW & Sons Crew #2)-Complete box tunnel-Continue excavation to stubs
Week of 11/15/2021
CSX/Randolph Rd.-Package A (SECA)-Begin first drive
Nebel St. & Marinelli Rd.-Package A (CW & Sons Crew #2)-Install conduits to tie onto stubs-Pour concrete-Backfill/temporary asphalt
Nebel St.-Package C (CW & Sons)-Continue getting trench to grade near sewer line-Begin excavation along substation wall
Barbara Spalholz
Looking for an update on when you expect to re-open Randolph Road west. I read that the intersection of Executive Blvd and Old Georgetown Road will be closed for 6 months starting March 22. I also read that 2 lanes will be closing on Nicholson though I couldn’t find the timeframe. If Randolph is not reopened before all this, people who have to commute east west along this corridor will have an even harder time than they have now.