Latest Update on the Western Workaround

Posted on by Amy Ginsburg

1 Comment

Bookmark and Share

FROM MCDOT: (Learn more about the Western Workaround project.)

Photo thanks to Don Weinstein

As of July 8, 2020, Executive Boulevard between Old Georgetown Road and Grand Park Avenue at the Marriott Hotel and Conference Center is permanently closed; look for the “DETOUR” signs that are rerouting traffic. On Monday, July 13, 2020, Corman Kokosing Construction Company began tearing up the old Executive Boulevard roadway in order to facilitate both new storm drain system construction and the start of work on the extension of Banneker Avenue. …

Read More

Western Workaround Construction Update

Posted on by Amy Ginsburg

Comments Off on Western Workaround Construction Update

Bookmark and Share

Below is the MCDOT notification on construction activities anticipated to begin June 15, 2020. The most important news is that Executive Boulevard will be closing around June 29. Yes, this is the third (or fourth?) date given for the closure, but we’re told that this one is going to stick. The second most important news is that nighttime work has been suspended.

Read More

Western Workaround Update from MCDOT

Posted on by Amy Ginsburg

Comments Off on Western Workaround Update from MCDOT

Bookmark and Share

Here’s a quick update on the construction of the Western Workaround.

  • Executive Blvd closure end May (delayed by two weeks)
  • VOB demo starts in two weeks
  • Night work continues under a noise mitigation plan, we are addressing a few complaints from residents at Pike and Rose
  • Coordinating installation of temporary signage with FRIT to make them less unsightly
Read More

Western Workaround Construction Continues Despite the Pandemic

Posted on by Amy Ginsburg

Comments Off on Western Workaround Construction Continues Despite the Pandemic

Bookmark and Share

The folks at MCDOT gave Friends of White Flint an update to the Western Workaround project, and we want to pass along the info to you.

The big news as that Executive Boulevard will be closing around mid-May. The closed part will extend from Old Georgetown Road to the Conference Center/M & T Bank.…

Read More

Western Workaround Construction Update

Posted on by Amy Ginsburg

Comments Off on Western Workaround Construction Update

Bookmark and Share

Construction activities anticipated for the next two weeks beginning July 28, 2019 on the Western Workaround/White Flint Project.

The utility infrastructure relocation and construction which began in August 2018 under the previous contract as Phase 1B still awaits completion. This work should finish by end of summer, 2019.PEPCO electrical construction located on the MNCPPC Aquatic Center property north of the Marinelli Road entrance has been completed—the contractor will return once PEPCO has installed a new power pole; the County is waiting on PEPCO’s schedule for pole placement.…

Read More

Western Workaround Update

Posted on by Amy Ginsburg

Comments Off on Western Workaround Update

Bookmark and Share

Construction activities anticipated for the next two weeks beginning July 14, 2019.

PEPCO electrical construction located on the MNCPPC Aquatic Center property north of the Marinelli Road entrance has been completed—the contractor will return once PEPCO has installed a new power pole; the County is waiting on PEPCO’s schedule for pole placement.…

Read More

What’s happening this week with the Western Workaround

Posted on by Amy Ginsburg

Comments Off on What’s happening this week with the Western Workaround

Bookmark and Share

Western Workaround/White Flint West construction activities anticipated for the next two weeks beginning June 2, 2019

The utility infrastructure relocation and construction which began in August 2018 under the previous contract as Phase 1B still awaits completion. This work should finish in summer 2019.

  • PEPCO electrical construction located on the MNCPPC Aquatic Center property north of the Marinelli Road entrance has been completed—the contractor will return once PEPCO has installed a new power pole; the County is waiting on PEPCO’s schedule for pole placement.
Read More

Western Workaround Construction Latest Update

Posted on by Amy Ginsburg

Comments Off on Western Workaround Construction Latest Update

Bookmark and Share

From MCDOT: Construction activities anticipated for the next two weeks beginning April 21, 2019

The utility infrastructure relocation and construction which began in August 2018 is near completion and will finish mid-Spring, 2019.

PEPCO electrical construction located on the MNCPPC Aquatic Center property north of the Marinelli Road entrance has been completed—the contractor will return once PEPCO has installed a new power pole.…

Read More

Western Workaround Construction Update

Posted on by Amy Ginsburg

Comments Off on Western Workaround Construction Update

Bookmark and Share

Are you seeing more orange traffic cones around Old Georgetown Road and Executive Blvd? Here’s why.

Some of the utility infrastructure relocation and construction which began in August 2018 is winding down and will finish in early Spring, 2019.

Construction continues on Towne Road behind Pike & Rose and along Old Georgetown Road.…

Read More

Western Workaround Work Update

Posted on by Amy Ginsburg

Comments Off on Western Workaround Work Update

Bookmark and Share

Construction activities anticipated for the two weeks beginning March 10, 2019. For additional information on the White Flint Project please visit http://www.whiteflintproject.com

The utility infrastructure relocation and construction which began in August 2018 will finish by the end of winter 2019.

Verizon telecommunications infrastructure construction located in the northbound right lanes of Executive Boulevard prior to Old Georgetown Road has been completed with only punch list items remaining-the contractor will return at a later date.…

Read More