Friends of White Flint

Promoting a Sustainable, Walkable and Engaging Community

P.O. Box 2761

White Flint Station

Kensington, MD 20891

Phone: 301-980-3768

Email: info@whiteflint.org


Tag Archives: western workaround

Western Workaround Construction Update

Posted on by Amy Ginsburg

Comments Off on Western Workaround Construction Update

Bookmark and Share

Construction activities anticipated for the next two weeks beginning July 28, 2019 on the Western Workaround/White Flint Project.

The utility infrastructure relocation and construction which began in August 2018 under the previous contract as Phase 1B still awaits completion. This work should finish by end of summer, 2019.PEPCO electrical construction located on the MNCPPC Aquatic Center property north of the Marinelli Road entrance has been completed—the contractor will return once PEPCO has installed a new power pole; the County is waiting on PEPCO’s schedule for pole placement.…

Read More

What’s happening this week with the Western Workaround

Posted on by Amy Ginsburg

Comments Off on What’s happening this week with the Western Workaround

Bookmark and Share

Western Workaround/White Flint West construction activities anticipated for the next two weeks beginning June 2, 2019

The utility infrastructure relocation and construction which began in August 2018 under the previous contract as Phase 1B still awaits completion. This work should finish in summer 2019.

  • PEPCO electrical construction located on the MNCPPC Aquatic Center property north of the Marinelli Road entrance has been completed—the contractor will return once PEPCO has installed a new power pole; the County is waiting on PEPCO’s schedule for pole placement.
Read More

Western Workaround Construction Latest Update

Posted on by Amy Ginsburg

Comments Off on Western Workaround Construction Latest Update

Bookmark and Share

From MCDOT: Construction activities anticipated for the next two weeks beginning April 21, 2019

The utility infrastructure relocation and construction which began in August 2018 is near completion and will finish mid-Spring, 2019.

PEPCO electrical construction located on the MNCPPC Aquatic Center property north of the Marinelli Road entrance has been completed—the contractor will return once PEPCO has installed a new power pole.…

Read More

Western Workaround Construction Update

Posted on by Amy Ginsburg

Comments Off on Western Workaround Construction Update

Bookmark and Share

Are you seeing more orange traffic cones around Old Georgetown Road and Executive Blvd? Here’s why.

Some of the utility infrastructure relocation and construction which began in August 2018 is winding down and will finish in early Spring, 2019.

Construction continues on Towne Road behind Pike & Rose and along Old Georgetown Road.…

Read More

Western Workaround Work Update

Posted on by Amy Ginsburg

Comments Off on Western Workaround Work Update

Bookmark and Share

Construction activities anticipated for the two weeks beginning March 10, 2019. For additional information on the White Flint Project please visit http://www.whiteflintproject.com

The utility infrastructure relocation and construction which began in August 2018 will finish by the end of winter 2019.

Verizon telecommunications infrastructure construction located in the northbound right lanes of Executive Boulevard prior to Old Georgetown Road has been completed with only punch list items remaining-the contractor will return at a later date.…

Read More

Western Workaround construction activities anticipated for the next two weeks beginning February 24

Posted on by Amy Ginsburg

Comments Off on Western Workaround construction activities anticipated for the next two weeks beginning February 24

Bookmark and Share

The utility infrastructure relocation and construction which began in August 2018 under the previous contract as Phase 1B continues. The work is scheduled to finish end of winter, 2019 and will take place alongside the work designated as Phase 2. Phase 1B work includes temporary daily lane closures on Executive Boulevard between Marinelli and Old Georgetown Roads at the following locations:

  • Verizon telecommunications infrastructure construction located in the northbound right lanes of Executive Boulevard prior to Old Georgetown Road now scheduled to wrap up on or about March 1, 2019;
  • PEPCO electrical construction located in the southbound right lane of Executive Boulevard between Marinelli Road and Banneker Avenue that began on January 2, 2019 with construction duration of six to eight weeks;
  • PEPCO electrical construction on the MNCPPC Aquatic Center property north of the Marinelli Road entrance that began on January 24, 2019 with construction tentatively scheduled to end March 15, 2009 as the contractor awaits design changes;
  • Washington Gas infrastructure upgrades in and along Old Georgetown Road both in the main line and at the intersection with Executive Blvd being completed by National Pipe Line (NPL)

The construction under contract for Construction Management at Risk (CMAR) with Corman Kokosing Construction Company which began in early January, continues on Towne Road formerly known as Hoya Street behind the Pike & Rose complex.…

Read More

Western Workaround Construction Should Begin Soon.

Posted on by Amy Ginsburg

3 Comments

Bookmark and Share

Find below MCDOT’s plans for the Western Workaround, Phase Two. Confused about what this oft-mentioned project will do?  You’re not alone.

Basically, the Western Workaround is going to get rid of the big curve on Old Georgetown Road near Executive Boulevard and open up Towne Road (the current dead-end road behind Pike and Rose.) The Western Workaround will create a new intersection with Executive Boulevard, Old Georgetown Road, and Towne Road.…

Read More

Info from Montgomery County Government on the Western Workaround

Posted on by Amy Ginsburg

Comments Off on Info from Montgomery County Government on the Western Workaround

Bookmark and Share

Montgomery County has started working on the first of two phases of the White Flint West Workaround transportation project, an effort designed to create a pedestrian-friendly community where residents and visitors can walk to work, shops and transit. The first phase is scheduled to be completed by the end of calendar year 2017.…

Read More

More info on the Western Workaround

Posted on by Amy Ginsburg

Comments Off on More info on the Western Workaround

Bookmark and Share

Hot off the presses from the Montgomery County Department of Transportation, more detailed information about the Western Workaround construction scheduled to begin in a couple of weeks.

The Conference Center surface parking lot will close in order to build a new, structured parking garage. The new garage will be six stories tall, house approximately 650 spaces, and will be accessible from both Executive Boulevard and Market Street.…

Read More

The Western Workaround is Coming — Really!

Posted on by Amy Ginsburg

6 Comments

Bookmark and Share

On November 8, the construction of the long-awaited Western Workaround begins! (Insert joyful music here.)

The Western Workaround realigns Executive Boulevard where it meets Old Georgetown Road. It creates a new street, Market Street, behind the Marriott Hotel and Conference Center. The Western Workaround also creates a rectangular parcel that will become the Gables Residential complex.…

Read More