Western Workaround Update from MCDOT
Here’s a quick update on the construction of the Western Workaround.
- Executive Blvd closure end May (delayed by two weeks)
- VOB demo starts in two weeks
- Night work continues under a noise mitigation plan, we are addressing a few complaints from residents at Pike and Rose
- Coordinating installation of temporary signage with FRIT to make them less unsightly