Pepco Substation Construction Updates

Pepco Substation Construction Updates

From Pepco:

Week of 07/05/2021

Randolph Rd. Near Parklawn Dr.-Package B -Anchor-Backfill/Temporary asphalt-Continue excavation

Nebel St./White Flint Substation-Package C (CW & Sons Crew)-Continue excavation south (CW & Sons)-Install conduit-Pour concrete-Form up for 2” oil lines-Continue box tunnel to substationNebel St. 100’ North of Old Georgetown-Package A (CW & Sons Crew)-Backfill/temporary asphalt-Continue excavation to stubs

Week of 07/12/2021

Randolph Rd. Near Parklawn Dr.- Package B -Anchor-Install conduit-Pour concrete-Backfill/Temporary Asphalt

White Flint Substation-Package C (CW & Sons Crew)-Complete box tunnel (Louden Tunneling)-Form up for 2” oil lines to be backfilled-Chester to install 2” oil lines-Backfill trench

Nebel St. 100’ North of Old Georgetown-Package A (CW & Sons Crew)-Continue excavation-Install conduit-pour concrete-backfill/temporary asphalt

Please feel free to reach out to Shamyra Edmonds, Project Ombudsman, for any questions or concerns about the White Flint Substation project at 202-643-3148 or sedmonds@cwsons.com.