The latest Pepco Substation Construction Update

The latest Pepco Substation Construction Update

Week of 07/19/2021

Randolph Rd. Package B -Anchor (Crew #1)– Continue excavation- Install conduit- Pour concrete

Nebel St. Near Randolph Rd.-Package B -Anchor (Crew #2)– Continue excavation- Install conduit- Pour concrete

Nebel St./White Flint Substation-Package C (CW & Sons Crew #1)– Pour concrete- Backfill/Temporary Asphalt- Continue 4-way box tunnel (Louden Tunneling)

Nebel St. & Old Georgetown-Package A (CW & Sons Crew #2)– Continue excavation- Install conduit- Pour concrete

Week of 07/26/2021

Randolph Rd.-Package B -Anchor (Crew #1)– Backfill/Temporary Asphalt- Continue excavation

Nebel St. Near Randolph Rd.-Package B -Anchor (Crew #2)– Backfill/Temporary Asphalt- Continue excavation

Nebel St./White Flint Substation-Package C (CW & Sons Crew)– Continue excavation- Install conduit

Nebel St. & Old Georgetown-Package A (CW & Sons Crew #2)– Backfill/Temporary Asphalt- Mobilize to Nebel St./Marinelli Rd.

Please feel free to reach out to Shamyra Edmonds, Project Ombudsman, directly for any questions or concerns about the White Flint Substation project at 202-643-3148 orĀ sedmonds@cwsons.com.